£30m upgrade of Biddulph wastewater treatment works announced

27 Nov 2026

United Utilities has announced plans to invest £30m to upgrade the wastewater treatment works in Biddulph.

The project, which is expected to be completed by winter 2029, will reduce the frequency of storm overflow spills into nearby Biddulph Brook. Historically, the overflow has operated more than 100 times a year, but the improvements are expected to cut spills by more than 90%.

The scheme includes the construction of two new stormwater storage tanks capable of holding around 12,000m³ of additional stormwater, equivalent to approximately five Olympic-sized swimming pools.

The additional capacity will help the sewer network cope better during periods of heavy rainfall, reducing the need for the storm overflow to operate when the system reaches capacity.

While final designs for the tanks are nearing completion, enabling works are already underway.

Maria Fletcher, Wastewater County Business Lead for United Utilities, said: “This project forms part of our investment in building a stronger, greener, and healthier North West.

“Biddulph has been one of the region's largest storm overflow spillers in recent years, but these improvements will significantly reduce spills and help improve water quality in Biddulph Brook, benefiting both local communities and the wildlife that depends on it.

“While the work is carried out, residents may notice increased activity around the site. We will do everything we can to minimise disruption and thank those living nearby for their understanding and patience.”