City Centre sewer upgrade completed early
A £1.3m investment at Aspin Lane has disconnected a storm overflow ahead of schedule, helping to improve water quality in the River Irk.
Located on the edge of Manchester's Green Quarter and NOMA district, the project removed surface water from the combined sewer network. This prevented the storm overflow from operating during wet weather, and it has now been sealed off.
Our contractors also managed to complete the work more than two months’ ahead of schedule, helping to minimise the disruption while the improvements were carried out.
Emma Oakes, Wastewater Business Lead for Greater Manchester, said: “We're delighted to have completed this important project, delivering benefits for both our customers and the local environment sooner than planned.
"I'd like to thank local residents, businesses and road users for their patience and understanding while we carried out these essential works. This project is another example of our commitment to improving rivers across Greater Manchester and creating a more resilient wastewater network for future generations."